From: route@monster.com
Sent: Thursday, April 07, 2016 12:03 PM
To: hg@apeironinc.com
Subject: Please review this candidate for: p6 Scheduler
This resume has been forwarded to
you at the request of Monster User xapeix03
|
|||||||
|
|||||||
|
|
|
||||||
|
||||||
|
William Keen
Jackson
18107 Wedgwood
Drive
jackslu@aol.com
Hammond, Louisiana
70403
Jacksonslu@msn.com
Home Phone 985-345-2845 Cell Phone
985-969-2222 Industrial Project
Controls, Construction, Estimator, Planner, Scheduler Primavera 7. Cost
Controls for Projects and over hauls. Use both critical path method and
critical path analysis in order to determine critical path for projects or
unit outages. Have used risk analyst pert master risk analysis 10/90
Monte Carlo through Primavera which is 50 / 50. Worked green field both
brown field outages and projects in refinery, chemical plants rolling steel
mills & power generation and transmissions along with T/A downstream along
with upstream projects and outages in the Gulf of Mexico in deep water. With
Shell Deep Water worked up stream off shore with deepwater projects as
Perdido Project Deep Water Spar in sixty nine hundred feet of water along
with the Mars Project. Can an able to produce a schedule of value in order do
schedule and man loads the cost of lump sum project. Capable of using the RFI
request for information that has a rough magnitude of order. Work within the
FEED front end engineering and design to the front end loading to the IPA and
to the detailed engineering portion then take it to the field for the
construction, EPC. QUALIFICATIONS: Over twenty five
years in the industrial construction field, petrochemical, oil refinery &
power generation up to two thousand megawatts. Extensive
knowledge of P&ID's and PFD’s piping ISO's orthographic and schematic
plan and elevation for structural or pipe and civil work also schematic &
orthographic for electrical and instrumentation. Twenty years of installation,
hydro test; sell off, precommissioning and start-ups as a supervisor.
Twenty years experience in estimating tools as PEP for pipe John Page.
Expert level in scheduling with Primavera P7 using exporting and importing
techniques learn through extensive work. Planning & writing work orders
and field requisitions using SAP and GEMTS I also use SAP for tracking
progress either in Engineering or Field Execution and am proficient in Sure
Trac. I am able to use Spreadsheets from Excel graphs from Primavera or
Excel. I use Word process using Microsoft Word. I am able to do
take offs and send inquiries for bid proposals budgetary lump sum or T &
M walk out with potential contractors and the client and set up bid
strategies for Projects or Unit outages. I am also able to walk and do
field planning and Construction and T/A schedules. EDUCATION:
Hammond High 1969 -1973
Southeastern Louisiana University 1973 - 1977
Member of Football Team 1973 - 1977
Captain of Football Team 1977
Associate Degree General Studies
TRAINING: Ø Advance training on
the MASC system. 1987 Kurtz and Steel Limited Ø Introduction to
PC’s River Parishes Vocational Technical School 1987 Ø Shell Wilmington,
Carson, California Kurtz & Steel Limited. 1990 Ø Supervisory
Training Skills and Techniques, Long Beach State
1991 Ø Primavera Finest
Hour - 1992 Jacobs
Engineering Ø Primavera P3 - 3.1
- 2000 & 2005 Zachry Construction Corp Ø Sure Track 2000 for
updating Zachry Project and T/A Ø Supervisor Training
of Surveying & Welding Codes & Procedure
ABC
Ø MSHA Training March
1st 2001 OSHA Training
August 1st 2000 Ø SAP Training @
Union Carbide and Air Products 2004 Shell 2006 &
2007
Ø Lock out Tag out
Training updated 2007 Ø Microsoft Project
2000 and 2005 Ø Richardson
Estimating and John Page 2004 Ø Primavera P5 – 2006
& 2007 & Primavera P6 2008 & 2010 and Primavera 6
(7.0) 2011 Ø HSE – 0039 – Water
Survival/HUET Helicopter Underwater Escape Training 2007 Ø Pass Port on
Request Ø TWIC March
2013 through March 10, 2018 Ø Advanced Safety
Auditing May 2008 Ø Security Pass
Port June 2012 Safety Council Ø GEMTS planning tool
Dow Chemical Zachry 2011 through 2013 Planning Tool Ø Association of
Reciprocal Safety Councils, Inc New Orleans and Baton Rouge 2013 I have completed my
work and I am actively seeking employment. Jacobs Engineering
at DOW SCO in Taft and now at the LAO plant, in Plaquemines LA. September 2011
through May 2013 I was one of three lead schedulers for the T/A Service Group I Scheduled the
Chlorine Unit Spring outage that was to start July 7, 2013 and go through the
end of August. I was downloading plans using a planning tool for this
and have over half the Jobs down loaded into the Schedule. The LHC3
Benzene System in which the scope included the Confined Space Entry for the
C-500 Column for inspection I completed the Poly East Plant which
contained two Trains four reactors and four pelting machines. I was
brought into the job for a turnaround but had to go straight into a Shutdown
for the Reactor logged up and had a giant piece of Plastic that had to be cut
out by pneumatic chainsaws, which being down a list develop that had to planned
and schedule Thus I was to schedule the outage and coordinate
activities. After this Shut Down anther occurred in the other Train # 2
in which work had to be done this also included planning and
scheduling. The original T/A was moved from February to May it was 18
days from Prime off to Prime on. The T/A came in under budget and Zero first
aids the Primary contractors were Turner, Jacobs who has the maintenance and
Sulzer who did the Rotation Equipment the Critical Path was the Reactor 3 and
the Rotor change out that was carried out by Dow and TNT cranes Zero first
aids. My duties were to input data and issue shift schedules to productions
and to contractors and to the Dow coordinators and to the Contractor
Coordinator.
I also was in charge of the loading barn in which pellets of poly were
loading into train cars. May of 2010 through
August 2011 I accepted a position in Iowa at Fort Dodge working under
contract through Universal Personnel to Koch at an Ammonia Nitrate Fertilizer
Facility in Fort Dodge, Iowa. In this position I was the lead scheduler the
SIS SB # 84 which stands for Safety Interruption System. Being that the
Plant was built in 1968 most insulation was asbestos and the paint was to be
considered to have a lead base primer. In this Project which had Front End
Loading and specified gates to past through for funding for design cost,
engineering and a significant update on its antiquated analogical control
system was to be upgraded to a DC control system that was engineered by
Yokagawa in which over 8000 IO points where to be changed out Excel had won
the bid for the electrical and instrumentation while JVI was to do the
mechanical that was engineered by to S&B out of Houston which included
rerouting over 160 control loops and 3800 fabrication welds and 400 field
welds along with installation of two DCS stations and the upgrading of Steel
Rack and supports. This was the first of a three facility work over for
the Koch Company Fertilizer Division. With all the field fabrication and
installation all welds pass NDT. Zero first Aids on the Project.
Think Resources (Contract Parson Inc), October, 2008 through March 2010 · Infrastructure
Scheduler for the Cold Roll Mill that is part of the 4 billion dollar
project. · The Project is in
the Civil and Structural Portion and the Duct Banks for the electrical needs
of the Mill and the commissioning of the over head cranes and the steps it
takes to become a production of Coiled Rolled Steel which is set to be Hot
Commissioned in 2010. This also contained the medium and low voltage feed and
the main electrical room. · The Civil was
complete in the Cold Roll Mill, which has a tandem mill a pickling line and a
continuous pickling line and an Acid Regeneration Unit along with a
boiler. · With the major
steel for one building being more that 12,000 tons and 100 thousand cubic
yards of Concrete. · All building are
trimming the decking and roofing, Major Equipment MEP and AOE buildings are
being done. Made sure that lighting and utility power was installed and
assisted Parsons in the underground duct banks. And Feed Conductors for
Over Head Cranes being installed by Crane
and Hoist. · My responsibility
was to go through P7 update with current view and review and analysis each
contractor in which I download using Primavera 7 from and xer. File · Quantities are
updated by the superintendents and I review with the contractors for
correctness. · Part of the CRM
Team and attend a Team Meeting with the Client and attend various
construction meetings, in which Daily Progress is discussed along with a look
ahead. · I also looked at
the daily construction reports from each area due to the fact that I have
CRM, Storage area 2 and Storage Area 1. · The Structural
portion of the Project was completed · Handled RFI and do
analysis for Delay notification and the contractor’s scope. · Review the AIA
forms for payment claims per the contract since each is Lump sum and use
general conditions or Unit rates for the extras. · I was working with
Crane & Hoist with the overhead crane company and produced a schedule
from the erectors of the rails for the over head cranes. · Conducted a three
week look ahead started here due to the fact that the schedulers before did
not require it. It gave a more detailed look at daily operations. · This Project is a
work in Progress just as the Schedule has to be a living document
due to the nature of the work and delays of weather and
mismatched fabrication and density of worker in areas. · The entire schedule
had to fit into the WBS of the IMS Integrated Master Schedule. In this
way an early late report is produced at the summary level for the upper
management. · Universal Personnel
Contracted to Shell Exploration Deep Water · One Shell Square in
New Orleans LA. May 2007 through October 2008 Which I worked for Shell (SIEP) Shell
International Exploration and Production for the EP Deep Water Brown Field
project services group. Schedules together for Mars Recovery and
working on the Perdido Project, which is the
deepest water Spar in the world as
of now. Anchored to the bottom at 6,800 feet · Using P6 for
scheduling and excel for planning of activities for the initial Hook Up of
the Quarter Habitable to the remainder of the Top Side work was done in third
quarter of 2008 and was scheduled to be complete by second quarter of
2009. · Worked with Lender
Jacobs engineering on the Fastball Project on Ram Powell. PMCC of Houston
Texas September 2005 thru May 2007 I was an
Independent Contractor as the Client Representative through Shell Global
Solutions. The project grew due to the GEP Closure Project that Jacobs
had started 3 years ago. With 11mm spent on the reroutes and the demo
of the unit being cancelled due to the fact that the 300# Section of EO-1 or
the new High Purity Ethylene Oxide Unit would now feed the EOG-03 unit due to
its design of only as a glycol unit not a unit to produce HEO. The
Project Premise was developed for a new design to have long routing of pipe
with eight new pieces of equipment and for the exchanges and condensers to be
reused. The new routed pipe
was routed along with the Electric and Instrumentation through the utility
rack which will encompass 22 thousand linear feet of pipe with and equally
amount of instrumentation and electrical work at a $25mm dollar range
approved after running a P50 Monte Carlo analysis and using the IPA
criteria. FB&D did the detailed design stage having just
completed FED, FEL, & IPA. The project was given a 4.25 range for
bench marking which is great for industry standards. The project
consisted of surgical demo of existing unit in which there will be a revamp
of an EO column. The engineering group of S &B has & their subsidiary
Ford Bacon & Davis have an EPCM contract. The Project went to
go to the field in September on the OSBL then follow up with and outage of
EO-3 in which 20 tie points were done. In January of 2007 the old
existing EO-1 was shut down and decontaminated for EO-1 Closure project which
is now part of the High Purity Ethylene Oxide Project will be demolished as
it has served its purpose for the last forty years. This increase the
cost of the project due to the rerouting of lines & E & I work. Project/Cord/Planner/Scheduler:
December 2004 to August 2005: Shaw Group I was the Project Lead of the Tiger
Demolition for UOP. We removed the last remains of Kaiser Aluminum
Company. I directed the daily operations of schedules and cost for
UOP. Had Cleveland Wrecking Company on lump sum bid with a 10% retainer
to share cost and profit of the scrap metal which is a commodity with the
price changing monthly. The salvageable equipment was sold at bid plus
mobilization of the equipment from industrial dryers, coolers, pumps,
instrumentation, drums, elevators, and machining equipment. PDG
was the asbestos company that did the asbestos removal. PDG was
completed by March 31st. Cleveland Demolition and the rest
of the Project finished @ 3400 gross tons of salvage and completed on time in
May. Planner, Scheduler:
July 2004 November 2004, Shaw Group completed the Inoes Fluor Overhaul, which
is a specialty Chemical Plant that manufactures KLEA 134a refrigerant.
I did the walk outs for all work inputted planning information into SAP and
created reports for tracking the cost. Shaw had the bulk of the work on
T&M but we also had eight sub contractors from NDT API inspections to
hydro blasting tubes. In which we replaced three bundles, which
encompassed lifting plans for weights and safety and radius of swing.
Critical Path was C510 Column work with G. E. doing the overlay Shaw Vacuum
out existing 304 Packing done in Acid Suites due to the HF that had remained
on the packing, which had to be decom with bull tanks in the storage area for
drums. The overhaul as the English calls them came in under budget and
3 days ahead of the P3 Schedule. I also had an update meeting and
a scheduling meeting for permits each day. We had 160 crafts and subs
on days and 40 crafts and subs on nights. The critical path worked 7 -
24 the rest of the overhaul was covered on 2 shifts of 6-10's. In
overhaul safety no OSHA recordable. Planner, Estimator,
Cost Control & Scheduler: January 2004 through July 2004: Shaw Group in
Pensacola at Air Products Chemical Plant in Pace Florida. I went there
and did the first T/A in two years that was successful and gave the unit back
a day early. It was under cost for the Project scope but over on the
Maintenance side due to lack of proper planning and scheduling and control of
add-ons. I did the estimating for civil, mechanical, and I&E for
projects. I did the field walk out for scoped work or using drawing or
P&ID's. Creating bid strategy and level 5 estimates for outages and
getting bids from sub contractors and developing the WBS for the project to
be completed during the Turn a Round coming up at Nitric Acid estimated,
planned, and creating the schedule Planner, Estimator,
Scheduler: August 2003 through December 2003 Zachry Construction Field
planned work Olefins unit, both cold side and hot side. My
responsibilities included estimating craft hours, cost material takeoffs,
scheduling and estimating. Field walk downs MO‘s magnitude of order
& Scheduling Mechanical, Civil, Scaffolding, Equipment. PIPING
E&I MOC & PSSR. Created drawings for drain pipe for shut down
of unit. Estimated Two Capital Projects Plus estimated Furnace work and
cogen modification for two projects to be done before major outage and
engineered by Jacobs Engineering Central office. Estimated a Project for a
new Silencer to be removed and revamped per the Client. Scheduler, Planner:
March 18, 2002 to June 2003 EXXON/MOBIL I estimated and
scoped out work for the #1Crude and #1Coker Units in Chalmette
Louisiana. The Class V Estimate for the Coker was 4MM and the Class V
estimated for the #1 Crude was 8MM. Tray Design Manufacturing and Delivery
were done on a fix fee. The Vessel work & Exchangers were done on
lump sum. Furnace work including pigging the furnaces one box and two
cans were bided out along with highly skilled pipe contractor mostly hot work
was fix fee. And the FMU’s field make up will be done with less skilled
personnel due to restriction put on piping were done lump sum including
project work. Companies supply of Best Practices Labor. I produced the shift
schedules for the execution team of the outages for the Coker # 1 Crude # 1
& Prefract unit at the time of the work. We were able to make the TAR
window without any OSHA recordable. I leveled scheduled the resource
manpower. Within the perimeter of the budget $12MM I also updated at the end
of each shift with a managers meeting being held @ 10:00 which production
reports from report writer using class and contractor in P3, I also use
graphic the backup graph or target and current views. This was done
during the Cat Cracker T/A & HF Alky T/A. in September through November. Scheduler, Planner,
Cost Control: May 15th 2001 through March 2nd 2002 Zachry I completed one
Cement plant Capital for Zachry Construction Corporation of San Antonio
Texas. Revamped the Drying Kiln from Natural Gas to Coke, Coal or
Used Tires in this way it would save money on the fuel that it took to
operate the kiln for the client. This required excavation of a tunnel
for a conveyor system for a rail car unloading platform. The
installation of ball mills and erection of a new larger plant, this included
large electromagnetic and strippers to remove the steel from the chopped used
tires. From October to March I worked on three coals fired boilers.
Changing out 600 tubes in the super and radiant heat section of the boiler
and installation of new High mega watt transformers for (SRP) Salt River
Project in northern Arizona Also had to
install car unloading equipment and installing new conveyors for the
coal yard in the Apache Reservation these outages came in under estimated
cost by 300k. In January I was transferred to Tampa Florida at the Big
Bend and the Gannon Station V operated by TECO Tampa Electric Company.
During this period I did estimating from Project work from the intake screens
to the DCS and adding on to the Control Room that could accommodate the new
Control Board for Operations. I also estimated and completed the new
Firewater system for the Gannon Station. A new conveyor for the moving of coal
from coal yard to the ball mill was installed. Turnaround &
Project Coordinator & Scheduler: Jacobs Engineering, September 20th, 2000 through
February 2, 2001 at Marathon Refinery in Garyville La. I worked in the
GHT Unit number 14, which a revamp of the unit making it capable of
increasing Unit production 20 % and to send feed to the new Coker unit that
is presently being constructed by other contractors. The unit work is
completed with the instrumentation and electrical which included additional
Motor control center and a new control house for the plant.
Following in suite the unit was able to start up January 27th, 2001 as planned. March 17, 1998 to
September 20, 2000 H. B. Zachry at the Union Carbide Plant in Taft, Louisiana As the turnaround
coordinator I was over all turnarounds. These consist of 5K man-hours
known as mini washes through 200K man-hours or more. These turnarounds
include cat changes of reactors repair per assessment recommendation plus all
regulatory requirements for condensers, towers, furnaces, piping,
instrumentation and electrical outages. I have completed the last year
with great success for (PF) performance factor and Production start up to
meet the schedule of the business group of that unit. These T/A‘s were
at Acrylics, Butonal, Olefins, PXC, SPU, Boilers, Oxide Cogen and Amines
units. At this facility there is over 200 duration days of turnarounds
within a twelve-month period.
May 1995 - March
1998 Jacobs Engineering Cost Controls at
Allied Geismar Hydrofluoric and Multi Products Plant. Responsible for
forecasting maintenance costs. I accomplished this by using historic data and
daily activities of maintenance. On team to develop Change order form to
automated system that is off-line with Allied MMS system. Help
establish forecast for year to date and for total year of 1996 showing actual
cost and forecast cost. This forecast is being used to set budget
target for 1997 budget. Total Maintenance for the facility was budget
of 20 million dollars for the fiscal year of 1997. I also had to cover cost
on the conveyor that brought spar into the plant.
April 1993 thru
April 1995 Estimate \ Planner \ Estimated planned and scheduled projects at
NPC For ISC at the
largest Hazardous Waste projects met the deadline set forth by the client. I
worked for Al Melancon in the estimating take offs and ordering the
electrical material for the Site. I was also the lead Primavera Scheduler for
the site.
1989 - 1993 Shell Plant,
Wilmington, California, from June 1989 through 1993 Brown and Root Industrial
Services I headed the planning team and became T/A Estimated planned and
scheduled Coker Unit Work for T/A consisted of 144,000 estimated man-hours
for which had a day shift and night shift. Project work included
upgrading super structure and installing 14,000 feet of pipe. The Coker Turn
a Round came in ahead of schedule and under the 13.5 million-dollar that was
budgeted for the Coker Unit Turn a Round. The T/A had a 1.36 incident
rate, which set a precedent for other complexes to compete against.
UNOCAL Plant, Carson California. Coordinated the flasher unit T/A that
was completed under the original budget of 6.5 million dollars. The T/A
consisted of major repair work on flasher column and fired
furnaces.
1981-1989 Brown and Root
Maintenance Shell Oil Norco, La. Worked up the trade of pipe fitter, welder
on Projects when I was transferred to Industrial Service of Brown and Root
and worked as a boilermaker. At this time I was given the chance as a
Pipe supervisor Pipe G.F. In 1987 I started planning T/A there I became
a Planner/ Scheduler planned piping, capital projects. Main Project was
the elimination of C3, C4 releases directly into atmosphere due to over pressure.
Estimated Scheduled the Hot feed Project at DU-5. This project
eliminated a bottleneck in piping to feed unit heat exchangers to obtain
higher product quality and quaintly in unit. Planned and estimated dual feed
header to Olefins units in order to increase the amount of feed to the fired
furnaces this was done by erecting additional structural iron and the
erection of 24 inch header with 6 inch risers going to each furnace.
Estimated, planned Polypropylene Turn a Round I hosted daily update meeting
on progress, cost, and craft disciplines. As a supervisor I was
responsible for clearing the utilities unit pipe rack and the isolation of
the cat-cracking unit after the explosion of 1988. I was in charge and
had responsibility of rebuilding the distribution and logistics pipe
rack.
1979
-1981
Brown and Root:
Georgia - Pacific
Plant
Plaquemine, La. I assisted in grass root as an Iron worker then became thru
school a Pipe Fitter for the construction of expansion at the Georgia Gulf in
Plaquemines LA.
DOW RESTRICTED |
|
|
||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Languages: |
Languages |
Proficiency Level |
|
English |
Fluent |
|
|
|